Product: TestProduct

Add group: Installation Tests

This group tests installation process. It should test installation procedure. Post-installation checks wellcome

Add group: Stress Tests

This group should verify the ability of the system to respond to bust input.

The main scope of this group is to check:

Add tag: Fresh installation

This tag defines initial condition: "product was not installed on the system"

Add tag: Script

This tag is associated with all test-cases that verify scripting language of our application

Add tag: Highest-priority

This tag is associated with highest-priority cases.

The cases with this tag are most important.

Component: TestComponent

Group: Installation Tests

Add case: confirmed, manual

Tag: Fresh installation
Summary
IS-OO1
Action
Run setup program
Effect
Program asks for path.
End

Add case: confirmed,manual

Tag: Fresh installation
Summary
IS-OO2
Action
Run setup program. In "Get Path" dialog press "Exit"
Effect
Installation process quits.
End

Group: Stress Tests

Add case: confirmed, automated

Requirement: RQ-RT-052
Tag: Highest-priority
Summary
STR-OO1
Action
Start few thousands of sessions to server.
Effect
Server handles all sessions. Response time must be < 10s
End

Add case: confirmed,manual

Tag: Highest-priority
Summary
STR-002
Action

100 interactive user sessions require function 15/0-112F.

Effect

System handles all request in reasonable time

No user tears his or her hair off while waiting for response